Strong gas flows achieved at Lockyer

Norwest, Lockyer Deep-1 Gas Discovery Well

Norwest Energy has advised that in preparation for production testing for its Lockyer Deep-1 conventional gas discovery well, perforating operations were conducted from 10-12 March.

The objective of the operation was to perforate the 25 metre Kingia reservoir gross pay interval from 4041.5 m to 4066.75 m MDRT utilising wireline-conveyed perforating guns, and to unload suspension fluid from the well.

Upon completion of perforating operations, early strong gas flow was achieved through a 34/64-inch variable choke.

The Kingia pay zone was perforated in three wireline runs, the first of which was conducted on 10 March 2022.

Upon completion of the initial 12 metre perforating run (4048.0 m to 4060.6 m MDRT) wellhead pressure built rapidly as the well unloaded the suspension fluid from the well.

The well flow continued until the flowing wellhead pressure stabilised at 4890psi with all suspension fluid removed from the well and continuous dry gas being produced to the flare pit.

The second and third perforating runs were completed on 11 and 12 March 2022, respectively.

The well was then flowed to the flare pit, gradually bringing up the flow rate to set on a 36/64-inch fixed choke with a stable flowing wellhead pressure of more than 4800psi.

Gas samples were obtained and the well shut in with a shut-in wellhead pressure of 5122psi.

The Kingia pay interval will be fully tested when the full SGS Well Testing Services production test equipment package arrives on site, with testing operations anticipated to commence on or around 25 March 2022.

The test will be conducted for a period of six days, following which the well will be shut in for a pressure build up period while the test equipment package is rigged down and demobilised.

At the end of the pressure build up period the pressure-temperature gauges will be retrieved and the well suspended for future completion as a producer.

Norwest managing director Iain Smith said these early results support the joint venture’s view that Lockyer Deep-1 will outperform once production testing commences.

“The rapid cleanup followed by early, high flow rates confirms that we are dealing with an extremely high-quality gas reservoir. We look forward to seeing what the well will deliver once production testing commences,” he said.

Subscribe to Oil & Gas Today for the latest industry news.